It is unknown when the first bridge was built across the Avon in Bristol, but the first stone bridge, Bristol Bridge, was built in the 13th century. Further downstream, the Avon Gorge formed a barrier between Clifton and Leigh Woods. In 1753 William Vick, a Bristol merchant, left £1,000 in his will to be invested until it had grown to £10,000, which was to be used to build a stone bridge across the gorge.
Plans
By the 1820s Vick's legacy was approaching £8,000. A stone bridge was estimated to cost considerably more than the sum available, but advances in the construction of suspension bridges made a crossing seem practicable. An Act of Parliament was obtained in 1829 to authorise construction and allow tolls to be levied. A competition was announced that year, and 22 designs were submitted, four of them by Isambard Kingdom Brunel.
Thomas Telford, who had designed the Menai Suspension Bridge, was asked to judge the entries. He rejected them all, taking the view that the gorge was too wide for a single span. He proposed his own design, with tall Gothic towers rising from the sides of the gorge to shorten the span. The cost of this scheme was beyond the means of the trustees.
A second competition was held in 1830. The judges initially preferred a design by Smith and Hawkes of Birmingham, but Brunel persuaded them to reconsider. In March 1831 he was declared the winner. His design had towers in the Egyptian style, surmounted by sphinxes. Brunel later described the bridge as his first child, his darling.
Construction
The foundation stone was laid on 21 June 1831. Work was interrupted later that year by the Bristol riots, which followed the rejection of the second Reform Bill by the House of Lords. The disturbances undermined confidence in the project and made it more difficult to raise money. Construction resumed in 1836, but by 1843 the funds had been exhausted. The towers had been built, but the chains had not been put in place. A temporary iron bar across the gorge, intended for use during construction, was used to carry passengers in a basket. Iron bought for the bridge was subsequently sold and used in Brunel's Royal Albert Bridge at Saltash.
Brunel died in 1859, and members of the Institution of Civil Engineers decided to complete the bridge as a memorial to him. In 1860 Brunel's Hungerford footbridge across the Thames in London was taken down to make way for a railway bridge, and its chains were acquired for use at Clifton. William Henry Barlow and John Hawkshaw revised Brunel's design, providing a wider and stronger deck and using three chains on each side rather than two. The sphinxes and much of the ornamental stonework were omitted.
Work resumed in 1862. A temporary platform was suspended across the gorge to assist in putting the chains in place. The bridge was completed in 1864 and opened on 8 December, with a procession crossing from Clifton to Leigh Woods.
Operation
The bridge was originally operated by the Clifton Suspension Bridge Company. From the outset, tolls were charged to meet the costs of the bridge. In 1952 the Clifton Suspension Bridge Trust took over its management under an Act of Parliament. The trust maintains the structure from toll income. Motor vehicles are charged to cross, but pedestrians and cyclists may use the bridge free of charge.
The bridge was built for horse-drawn traffic but has continued to carry motor vehicles, subject to a weight limit of four tonnes. It is a Grade I listed building. In 2002, work on the Leigh Woods abutment revealed a series of vaulted chambers whose existence had been forgotten. The chambers were built into the tall sandstone abutment supporting the western tower.
Celebrations
The bridge's centenary in 1964 was marked by celebrations and a commemorative postage stamp issued by the General Post Office. In 2006 the bridge was a focus of celebrations marking the bicentenary of Brunel's birth. A new illumination system, using light-emitting diodes to pick out the towers and chains, replaced the earlier lighting.
In December 2014 the 150th anniversary of the opening was marked by a fireworks display and a procession across the bridge. A visitor centre on the Leigh Woods side opened in the same year, with displays on the history, construction and maintenance of the bridge.